The Boeing Company 747
11 km E Melbourne Airport, VIC · 2012-09-09·N409MC
What happened
ATSB summary, verbatimDescent below minimum permitted altitude involving Boeing 747, N409MC, 11 km E of Melbourne Airport, Vic. on 9 September 2012 (Operational non-compliance) What happened On 9 September 2012, a Boeing 747 freight aircraft, operated by Atlas Air and registered N409MC, was approaching runway 34 at Melbourne Airport, Victoria, following a flight from Auckland, New Zealand. The flight crew was conducting the LIZZI FIVE VICTOR standard arrival route (STAR) procedure that included a requirement not to descend below 2,500 ft until past the SHEED waypoint. They were issued clearance by air traffic control for a visual approach for runway 34 from the SHEED waypoint, conditional on not descending below 2,500 ft before SHEED. The flight crew read back the clearance without including the minimum altitude before passing SHEED and the controller did not query the incomplete read back. The flight crew initiated the visual approach and descended below the stipulated minimum of 2,500 ft prior to SHEED. What the ATSB found The ATSB found that the United States-based flight crew did not hear the requirement of the clearance to not descend until after passing the SHEED waypoint. Instead they read back what they believed to be a clearance for an immediate visual approach from their present position. This is a normal instruction during operations in United States airspace. The crew continued their approach to Melbourne Airport based on this understanding. There was no loss of separation with any aircraft. The lack of detection by the controller of the crew’s incomplete read back represented a missed opportunity to alert the flight crew to not descend below 2,500 ft until after the SHEED waypoint. Visual approaches from STARs are available elsewhere in Australia, but are not available for use by international operators of large jet aircraft. The approaches via SHEED to runway 34 at Melbourne are the only exception to this rule and are implemented with few additional defences to address the increased risk associated with this type of approach. In addition, the flight profile required from the SHEED waypoint to runway 34 is steeper than other approaches of this type in Australia, requiring a higher rate of descent. This increases the likelihood of an unstable approach. Safety message This occurrence highlights the importance of a shared understanding of a clearance between pilots and air traffic controllers, and the factors which may affect this understanding. It also underlines the importance of a thorough risk assessment in support of the design, modification and promulgation of approaches so that any increased risk is identified and addressed. On 9 September 2012, the flight crew of a Boeing 747-47 UF/SCD freight aircraft, registered N409MC and operated by Atlas Air Inc. (Figure 1), conducted a flight from Honolulu, United States (US), to Auckland Airport, New Zealand. From Auckland the flight continued to Melbourne Airport, Victoria, with an estimated time of arrival of about 1800 Eastern Standard Time. [ 1 ] The aircraft was being operated as a freight flight for an Australian operator and had four US flight crew on board due to the length of the flight. Figure 1: B747, US-registered N409MC Source: Xing Li As the aircraft tracked towards Melbourne, the crew were cleared by air traffic control (ATC) to conduct a LIZZI FIVE VICTOR standard arrival route (STAR) for the descent from cruising altitude to the landing (Figure 2). The first officer was the pilot flying and the captain the pilot not flying. At 1720 the crew specified a requirement to ATC for them to use runway 34 instead of runway 27 which, due to the generally more favourable winds affecting that runway, was also in use. The crew reported that their requirement was based on the greater runway length available on runway 34, and the aircraft’s high landing weight. At 1724, ATC asked the crew if they were prepared to accept the visual approach that formed the final segment of the STAR. The crew confirmed that they could accept the visual approach. Figure 2: LIZZI FIVE ALPHA, DELTA AND VICTOR STAR ARRIVALs chart (RWY 34 VICTOR, which incorporates the SHEED waypoint, highlighted in red and the position of waypoint SHEED highlighted in green) Source: Jeppesen (modified by the ATSB) At 1735, as the aircraft descended through flight level (FL) 200 [ 2 ] and passed 65 NM (120 km) from Melbourne, the crew requested a change of approach to an area navigation global navigation satellite system (RNAV GNSS) instrument approach. This approach provided for an 8 NM (14.8 km) final approach track to runway 34. The crew reported requesting this approach because of the atmospheric haze and the setting sun to the west, which reduced their forward visibility. The crew were informed by ATC that unless they advised that the change was an ‘operational requirement’ their request for the RNAV GNSS approach was not available. ATC was concerned that the change would have caused delays to the arrival sequence of following aircraft. The crew confirmed acceptance of the original clearance via the LIZZI FIVE VICTOR STAR and by implication the associated visual segment. ATC cleared the crew to continue their descent to progressively lower altitudes before instructing them to ‘descend to and maintain 2,500 ft’ (Figure 3). The flight crew read back the clearance to descend to 2,500 ft but not the requirement to maintain that altitude. Figure 3: Aircraft radar track Source: Airservices Australia (modified by the ATSB) Visual guidance to runway 34 was provided by sequenced lead-in strobe lights to assist crews conduct a visual turn onto final and a precision approach path indicator (PAPI) system for approach slope guidance [ 3 ] . At 1747, when the aircraft was 7 NM (13 km) from the airport, ATC instructed the crew to report sighting the lead-in strobe lights. At that time the aircraft was about 4 NM (7.4 km) from the SHEED waypoint, which was located at the threshold of runway 27 at Essendon Airport. SHEED was the final waypoint before the visual segment of the STAR procedure. Recorded radar data showed the aircraft deviating left of track from about 3 NM (5.5 km) before SHEED, which the flight crew reported was to provide ‘more room’ for descent during the visual segment of the STAR. The LIZZI FIVE VICTOR STAR had a minimum altitude restriction that required aircraft to cross the SHEED waypoint at or above 2,500 ft (Figure 2). The STAR procedure stated that if the flight crew had not obtained visual reference at SHEED, they were to initiate a missed approach procedure (Figure 2). At 1748, when the aircraft was about 1 NM (1,852 m) before SHEED, the controller asked the flight crew if they had seen the lead-in strobe lights. The crew reported sighting the strobe lights, having just observed them. The controller then instructed the flight crew ‘…from SHEED you’re cleared visual approach for runway three four’. The crew read back ‘clear visual’ and configured the aircraft for the approach by extending the landing gear and approach flap. The first officer also disengaged the autopilot and initiated a descent for the visual approach. The controller did not query the flight crew in relation to providing a corrected read back to include the conditional clearance that descent below 2,500 ft was only authorised ‘…from [after passing] SHEED’. At about 1749 the aircraft descended below 2,500 ft when still about 1.6 km before SHEED and was descending through 1,900 ft when passing abeam SHEED. The aircraft’s maximum deviation to the left of the arrival track was about 500 m. The pilot of a helicopter operating at 1,500 ft in the Essendon control zone saw the B747, thought it was lower than expected and descended the helicopter to 1,000 ft to ensure adequate separation. The aircraft landed on runway 34 at 1751. __________ • Eastern Standard Time (EST) was Coordinated Universal Time (UTC) + 10 hours. • At altitudes above 10,000 ft in Australia, an aircraft’s height above mean sea level is referred to as a flight level (FL). FL 200 equates to 20,000 ft. • The visual approach guidance provided by the runway 34 Pr
Findings
the ATSB's findings: contributing factors and other factors that increased risk, verbatimContributing factors • The flight crew did not perceive the clearance requirement to not descend below 2,500 ft until passing the SHEED waypoint and descended prior to this point. • Air traffic control did not detect or correct the flight crew's incomplete read back of the clearance for the visual approach to runway 34 from the SHEED waypoint, missing an opportunity to prevent the descent prior to the SHEED waypoint. • Unlike other Australian standard arrival routes that included a visual segment, the visual approach to runway 34 at Melbourne via the SHEED waypoint could be issued to super or heavy jet aircraft operated by foreign operators, despite there being more safety occurrences involving the SHEED waypoint than other comparable approaches. [Safety issue] Other factors that increased risk • The LIZZI FIVE RWY 34 VICT OR ARRIVAL required a 3.5° descent profile after passing the SHEED waypoint for visual approach to runway 34 at Melbourne, increasing the risk of an unstable approach. [Safety issue] The safety issues identified during this investigation are listed in the Findings and Safety issues and actions sections of this report. The Australian Transport Safety Bureau (ATSB) expects that all safety issues identified by the investigation should be addressed by the relevant organisation(s). In addressing those issues, the ATSB prefers to encourage relevant organisation(s) to proactively initiate safety action, rather than to issue formal safety recommendations or safety advisory notices. All of the directly involved parties were provided with a draft report and invited to provide submissions. As part of that process, each organisation was asked to communicate what safety actions, if any, they had carried out or were planning to carry out in relation to each safety issue relevant to their organisation. Where relevant, these safety issues and actions will be updated on the ATSB website as information comes to hand. The initial public version of these safety issues and actions are in PDF on the ATSB website.
Safety recommendations
2 issuedwhat changed because of this accident- AO-2012-120-SI-01issued
Who it affects: | All foreign operators of super or heavy jet aircraft conducting a visual approach to runway 34 at Melbourne via the SHEED waypoint Status: | Adequately addressed Design of the LIZZI FIVE RWY 34 VICTOR ARRIVAL at Melbourne Airport The LIZZI FIVE RWY 34 VICTOR ARRIVAL required a 3.5° descent profile after passing the SHEED waypoint for visual approach to runway 34 at Melbourne, increasing the risk of an unstable approach. Issue number: |
- AO-2012-120-SI-02issued
Who it affects: | All flight crew of large jet aircraft conducting the visual approach via SHEED waypoint to runway 34 at Melbourne. Status: | Adequately addressed General details Date: | 09 Sep 2012 | | Investigation status: | Completed | Time: | 1748 EST | | Investigation type: | Occurrence Investigation | Location ( show map ) : | 11 km E Melbourne Airport | | Occurrence type: | Operational non-compliance | State: | VIC | | Occurrence class: | Airspace | Release date: | 01 Sep 2015 | | Occurrence category: | Incident | Report status: | Final | | Highest injury level: | None | Aircraft details Aircraft manufacturer: | The Boeing Company | Aircraft model: | 747 | Aircraft registration: | N409MC | Serial number: | 30558/1242 | Type of operation: | Air Transport High Capacity | Damage to aircraft: | Nil | Departure point: | Auckland, NZ Destination: | Melbourne, VIC
What an account opens
The Explorer account is free and reads the whole record. The recorders, the Analyst and the Casebook are the paid plans.