What happened

ATSB summary, verbatim

Operational non-compliance, Perth Airport, WA, 9 May 2008, PK-GEF, Boeing Company 737-8CX Summary On 9 May 2008, a Boeing Company 737-8CX aircraft, registered PK-GEF, was being operated on a scheduled passenger service between Denpasar, Republic of Indonesia and Perth, WA. On board were two flight crew, six cabin crew and 76 passengers. The flight crew reported that, once established in the cruise, they reviewed their briefing material and noted that the threshold for runway 21 at Perth was displaced due to runway works. On approach to land at Perth, the aerodrome controller issued the flight crew with the landing clearance, '... runway 21 displaced threshold, cleared to land'. When the aircraft was about 15 seconds from touchdown, the flight crew questioned the presence of cars on the runway and conducted a go-around. On the second approach, the flight crew were again issued the landing clearance '... runway 21, displaced threshold, cleared to land'. The aerodrome controller recalled observing the aircraft on what appeared to be an approach to land on the closed section of the runway and instructed the flight crew to go around. The go-around instruction also included information to assist the flight crew in identifying where the aircraft was to be landed. That additional information, together with the high workload being experienced by the flight crew at that time, may have momentarily confused them, with the effect that they did not assimilate and act on the instruction to go around. As a result of this incident, the airport operator undertook a number of safety actions. Those actions included: the review of its dispatch of Method of Works Plans (MWOP) to relevant stakeholders; the implementation of a more robust MWOP receipt and acknowledge system; and the establishment of a project safety group in support of all critical airside works.

Findings

the ATSB's findings: contributing factors and other factors that increased risk, verbatim
Findings From the evidence available, the following findings are made with respect to the operational noncompliance involving the Boeing Company 737-8CX aircraft, registered PK-GEF, which occurred at Perth Airport, WA on 9 May 2008, and should not be read as apportioning blame or liability to any particular organisation or individual. Contributing safety factors • The existing runway 21 threshold and touchdown markings were not required to be obscured and were clearly visible to the flight crew. Those markings continued to provide approach and landing cues to the normal touchdown zone, which was located within the runway works area. [Safety issue] • The use of the 6 m closed runway markings in lieu of the recommended 36 m markings increased the risk of a flight crew conducting a visual approach to the permanent threshold/touchdown area. [Safety issue] Other safety factors • The combination of the instruction to go around with landing information, and high workload at that stage of the approach, may have momentarily confused the flight crew, with the effect that they did not assimilate and act on the instruction to go around. • The distribution system that was used by the airport operator to disseminate the Method of Working Plan (MOWP) did not ensure that all users of the airport were appropriately notified of the planned runway works. [Safety issue] • There was no follow-up action taken by the airport operator to address the lack of responses from aircraft operators to the MOWP, as required by the receipt and acknowledgement system. • There was no evidence of any consideration in the MOWP of the effect of the runway 21 works on the final approach profile necessary from the MDA of the runway 21 localiser (LLZ) approach. [Safety issue] Other key findings • The runway markings associated with the MOWP were in accordance with the regulator’s Manual of Standards (MOS). - 18 - - 19 -