FlarePath
UK AAIB AAIB-2013-GCELF · UK AAIB · Field investigation

Boeing 737-377

On departure from Leeds Bradford Airport · 2013-08-02·G-CELF

Open this case in FlarePathSign inThe record below is free to read. An account opens the recorders, the photographs and the Analyst.
0
fatal
0
serious
No injury
highest injury
—
damage

What happened

AAIB synopsis, verbatim

Summary: The aircraft suffered an electrical failure after departure, which led to the loss of the commander’s primary flight instruments, navigation equipment and other electrical services. There was also a smell of electrical burning in the passenger cabin, so an immediate return to the airport was carried out. The loss of power was caused by a fatigue failure of the terminal lug on the end of the No 1 generator phase ‘A’ ground cable. An inspection revealed a number of other lugs which had cracked in the same location, two of which were close to failing in the same manner. The lugs had probably cracked as a result of a combination of engine vibration, a rough surface finish and bending of the lug during installation.

Conclusion

the AAIB's conclusion, verbatim
Analysis Operations The initial loss of the AT was recognised by the commander who was aware that it was not a ‘no go’ item in the Minimum Equipment List (MEL) and expected to continue the flight. As his instruments and other services failed, he realised that there had been a significant electrical failure although he did not recognise the situation as one which was covered in the abnormal checklist. The PF continued to fly the aircraft, using his instruments, and ATC were notified of the situation. The crew agreed that there was no abnormal procedure for their circumstances and that they should return to Leeds Bradford Airport. At that stage, there was no urgency to return and the Standard Operating Procedures (SOPs) regarding briefing the cabin crew were carried out as normal. When the SSC made the commander aware of the burning smell, the flight crew decided to expedite their return and transmitted a PAN call. From his training background, the commander knew that 140 kt was a safe approach speed and would not be runway limiting. When the No 1 generator tripped offline, the commander carried out the abnormal procedure and the FMC became available, enabling the appropriate approach speed to be obtained.