UK AAIB AAIB-2005-GBGMN · UK AAIB · Field investigation

British Aerospace HS.748 Series 2A

East Midlands Airport, Derbyshire · 2005-01-28·G-BGMN

Open this case in FlarePathSign inThe record below is free to read. An account opens the recorders, the photographs and the Analyst.
0
fatal
0
serious
No injury
highest injury
Minor
damage

What happened

AAIB synopsis, verbatim

British Aerospace HS.748 Series 2A, G-BGMN Summary: The aircraft’s left over-wing emergency escape hatch detached from the aircraft during takeoff from East Midlands Airport. A deferred technical defect in the aircraft’s pressurisation system meant that the loss of the hatch, was only discovered after landing at Ronaldsway Airport on the Isle of Man. The investigation established that a protective cover, in the cargo area, intended to prevent inadvertent operation of the over-wing emergency escape hatch handle, was not attached prior to loading and that movement of the cargo probably caused the handle to move to the ?open? position, allowing the hatch to detach from the aircraft. The investigation also established that a number of deficiencies existed in the operator’s training and oversight of contracted loading staff. Four safety recommendations are made.

Conclusion

the AAIB's conclusion, verbatim
Analysis Assuming that the emergency hatch was correctly closed at the beginning of the loading operation and taking account of the absence of damage both to the structural aperture and lack of pre-incident damage to the hatch, the only way in which the latter could have opened was by the inner handle moving inboard and rotating downwards, (ie as in the normal sequence of hatch opening from within). Both hatch covers were detached and loose in the cabin when the aircraft left Ronaldsway. They may have become detached due to worn Velcro pads, though there is also the possibility that they could have been deliberately removed to allow more light into the cabin during night loading operations if the aircraft was not electrically powered. Although the aircraft did experience problems with the ground power supply at East Midlands, it was powering the aircraft, and hence the lighting system, during loading. Had this not been the case loading staff there would have ceased operations, in accordance with local procedures. No-one at East Midlands reported fitting the covers, so although loading personnel there were divided about the state of the covers, they were almost certainly not in position covering the hatches when loading commenced. The left hatch handle would therefore have been exposed to contact with items of freight loaded in the cabin. The curved shape of the cabin side above the aperture, coupled with any settlement of freight items during loading, would have permitted articles of certain shapes and dimensions to have moved downwards and outboard in such a way as to have gradually positioned themselves between the handle and the hatch structure. Under such circumstances, the handle would readily move away from the stowed position, pivoting inboard, as settlement of load items continued. Thereafter, such settlement would have been capable of rotating the now protruding handle downwards. If sufficient rotation took place, the over- centring action of the latches would occur, permitting the hatch to open outwards. Presence of any positive cabin pressure differential would increase the force required to over-centre the catches and initiate release of the hatch above that required without pressurisation being present. It is presumed that no differential pressure was present at this point. The location from which the hatch was recovered indicates that all or most of the take-off ground run had occurred when the hatch detached. Since considerable rotation of the handle is required to over-centre the catches, it would appear that inboard movement and hence un-stowing of the handle most probably occurred during loading, possibly accompanied by some degree of initial handle rotation. The nature of the loading operation results in the hatch area becoming obscured by freight as soon as that section of the aircraft is loaded above the window line. The technical log entry and the low cabin pressure differential experienced by the flight crew on the previous leg were likely to have created an expectation of similar problems during the incident flight. It thus came as no surprise to the crew that no cabin pressure differential was achieved on the flight to the Isle Of Man and accounts for the fact that they did not consider the possibility that a faulty hatch or door may have been responsible for the lack of pressurisation. Clearly the importance of the protective covers over the hatches was not appreciated by the loading staff at East Midlands. It was notable that, although the loading

Safety recommendations

4 issuedwhat changed because of this accident
  • AAIB 2005-140issued

    The Civil Aviation Authority should ensure that Emerald Airways reviews its procedures for initial training and periodical examination of contracted loading staff at outstations, including the provision of written instructions and aircraft technical training, to ensure that Emerald Airways fully meets the responsibilities placed on it by JAR-OPS 1.205.

  • AAIB 2005-141issued

    Emerald Airways should review its safety management system with a view to accelerating the current audit schedule for outstations, and conduct a risk assessment of them all to establish those most ′at risk′, prioritising audit inspections accordingly.

  • AAIB 2005-142issued

    Emerald Airways should take immediate action to ensure that applicable, detailed and current written instructions are readily available to loading staff at all bases and outstations.

  • AAIB 2005-143issued

    The Civil Aviation Authority should pursue the findings of its own audits of Emerald Airways’ loading procedures, particularly in respect of the provision of written instructions, with a view to enforce compliance as soon as practicable.