What happened

AAIB synopsis, verbatim

AS332L Super Puma, G-PUMB

Conclusion

the AAIB's conclusion, verbatim
Discussion At the time that this incident occurred, the operator was in the process of reviewing and revising its maintenance control procedures as a result of an earlier minor incident arising from an uncompleted maintenance procedure. (G-PUMK, reported in AAIB Bulletin 7/98) The operator notified the AAIB of this incident to G-PUMB immediately it had occurred. It became clear during the investigation that a number of issues had some influence on why the coupling bolts had not been fitted and their absence not detected. The crucial points in the maintenance sequence which led to this omission appeared to be:- a The departure of the unlicensed man from the late shift before any work to remove the splined coupling had been done. b His return on early shift, the following morning, after a shorter than usual overnight break, to find what he thought was the expected situation. c The deviation of the late shift supervisor from normal shift changeover practice. d The consequent unavailability, to the unlicensed man, of handover information to clarify the exact status of the job and the preparations, made by the third man, to progress it. e The unsupervised progress of the job during the first 3 hours of the early shift, which precluded intermediate inspections because the authorised inspector was not on shift. f The lack of identification, on worksheets, of vital inspection stages during progress of the maintenance. The relatively small size of the shift gave rise to situations where unlicensed engineering staff might be working remote from supervision, particularly during the process of shift changeovers. The unlicensed engineer involved in this incident was in this situation and was placed in the position where he was working effectively alone for three hours during the early part of the Monday morning shift. It was during this time that he had deviated from what had been his normal practice for refitting the splined coupling and had experienced the distraction of having difficulty finding the tooling for refitting the shaft. It was known that there would be no personal hand-on of the job from the third man to the unlicensed man and there was no intention on either man's part to write or expect a handover note as the established procedure for passing handover information was through the shift supervisors. The two men had parted at 2100 on Saturday evening with the unlicensed man having an expectation of how far the job would have progressed, but the third man, quite reasonably, having the intention to proceed as far as he could. Thus, with no available handover information to tell the unlicensed man the extent to which the third man had progressed the job and done preparatory work and provisioning, he was left thinking, mistakenly, that he understood the position fully when alone, very early in the morning, and after only a short break for rest and sleep The deviation from normal practice, in the way the supervisor changed from late to early shift, defeated the established company procedure for handover information to be transmitted. Another factor which came to light during the investigation was the placement, on the workbench, of the bolts for the shaft reassembly and fitting. There was a mismatch between what the third man believed he had left overnight against what the unlicensed man recollected finding in the morning. The presence of bolts on the workbench should have acted as a prompt that there were some bolts unfitted. However, the unlicensed man could not remember seeing any such bolts and no trace of them was found during the investigation. There was no evidence to suggest that the bolts were disturbed during the night shift and their disappearance has not been resolved. It is probable, however, that if a handover note had been written it would have highlighted the existence of the bolts and, whether they had been present or absent, they would have been brought to the unlicensed man's attention. The fact that the unlicensed man did not have to undo any bolts before removing the splined coupling from the shaft that morning may have constituted the absence of another potential reminder that bolts were needed to attach the coupling to the shaft. There was found to be some uncertainty on the part of the licensed man as to what he was certifying when his signature was placed against work executed by the unlicensed man whilst working under his charge. Furthermore, all the engineers involved appeared to have a different perception of what a licensed man's signature indicated as against what the company Quality Control believed it meant. It was also observed that the worksheets for the various tasks were not entirely consistent in format and whilst the intention of part of these inconsistencies was to point up differences in the way the tasks were supposed to be viewed on the part of the certificating engineer, this had not been appreciated by them. A f
In FlarePath for this case

What an account opens

The Explorer account is free and reads the whole record. The recorders, the Analyst and the Casebook are the paid plans.